Guide · Multiple job sites
How to track employee hours at multiple job sites
To track hours at multiple job sites, record a start, an end and a location for every stretch of the day, then split paying from costing. Pay covers the whole shift, including drives between sites. Costing is a rule you choose for assigning each minute to a job. Write that rule down once so every foreman allocates the same way.
Last updated By ZeroBadge
This is general information, not legal advice. Laws differ by state and change over time. Check the primary sources below and talk to an employment lawyer about your situation.
What do you need to record when a crew works several sites?
You need a start, an end and a location for every stretch in between, so that one shift can be split into the places it was spent. A single start and end plus one job number is how a three-stop day ends up charged to whichever job the foreman remembers last.
- One shift, many stretches. A move from Job A to Job B inside the day is a transfer, not a new shift.
- A location per stretch. Each job, the shop, the yard and the supply house you use most.
- Drive time as its own line. It is paid, and how you charge it is a separate decision.
- Who moved and when. The record should show the day a worker's main job changed, so crew counts by site stay honest.
The general version of this, across every method, is in the construction time tracking guide.
How does each tracking method split a day across jobs?
Each method splits the day differently, and each breaks in a different place. The split is only as good as whoever, or whatever, does the splitting.
| Method | How the split happens | Where it breaks |
|---|---|---|
| Paper sheet with job lines | The worker writes hours against each job at day's end | Estimated from memory, usually in round half hours |
| Foreman entry | The foreman assigns time for the crew | Whole crew goes to one job unless he splits it, and he is rarely at both sites |
| Phone app with job switching | The worker taps to change jobs | Missed taps leave all the hours on the last job selected |
| Site clock at each job | Each clock records only its own site | Drive time and the supply house fall between clocks |
| Location-based record (geofence) | Time is placed by where the worker was | Needs coverage and sites drawn in advance; dead zones leave gaps to fill |
Which one suits you depends on how often crews move. The methods comparison puts eight options on the same terms.
Is the pay rule the same as the job cost rule?
No. The pay rule decides which minutes the worker is paid for, and the cost rule decides which job those paid minutes are charged to. Mixing them up is why a foreman will say a drive was free when he means it was not charged to anyone.
On pay, federal rules are clear on the main point. Travel from job site to job site during the workday counts as hours worked (29 CFR 785.38), and normal travel from home to work does not (29 CFR 785.35). State law and union agreements can add more. Is travel time between job sites paid goes into the detail.
On cost, the law is silent. That is your call, and it needs a written rule. Three common ones:
- First site gets the day. Simple, and wrong whenever the crew moved.
- On-site time only. Each job is charged for minutes inside it. Drives and supply runs sit in an overhead bucket nobody owns.
- On-site plus the leg that led there. Each job takes its own on-site time, the drive to it and any supply run made for it. Shop load-out goes to the first job.
What does one day look like when it is charged to two jobs?
Here is a journeyman's seven-stop day, charged under the first rule and the third. The numbers are illustrative, and the hourly rate is an assumption you should replace with your own loaded rate.
Journeyman, 7:00 AM to 3:30 PM (510 minutes)
- 7:00 to 7:20Shop, loading the truck for Job A (20 min)
- 7:20 to 7:45Drive to Job A (25 min)
- 7:45 to 11:30On site at Job A, rough-in (225 min)
- 11:30 to 11:45Drive to the supply house (15 min)
- 11:45 to 12:20Supply house, fittings for Job B (35 min)
- 12:20 to 12:45Drive to Job B (25 min)
- 12:45 to 3:30On site at Job B (165 min)
Hours and cost by job under two allocation rules
- Rule 1, first site gets the day
- Job A: 510 min = 8.50 h; Job B: 0 h
- Rule 3, Job A
- 20 + 25 + 225 = 270 min = 4.50 h
- Rule 3, Job B
- 15 + 35 + 25 + 165 = 240 min = 4.00 h
- Check
- 270 + 240 = 510 min
- Assumed loaded rate
- $55.00 per hour (replace with yours)
- Job A cost, Rule 1 vs Rule 3
- 8.50 h x $55 = $467.50 vs 4.50 h x $55 = $247.50
- Job B cost, Rule 1 vs Rule 3
- 0 h x $55 = $0 vs 4.00 h x $55 = $220.00
- Cost moved from Job A to Job B by the rule
- $220.00
The worker is paid for all 8.50 hours under either rule. Only the job the cost lands on changes.
Do that for six workers over a week and Job B's labor, and its margin, looks very different. For how loaded rates are built, see how to calculate labor burden.
Where does the paid day start for a worker who reports to the shop?
It starts where your rule says work begins, and under federal rules that is usually at the first place the worker is required to report, not at their front door. Travel from home to the first job site is normally commuting, but a required stop at the shop to pick up tools or get instructions makes the travel from the shop part of the day.
| Situation | Paid day starts | Why |
|---|---|---|
| Worker drives from home straight to Job A | On arrival at Job A | Normal travel from home to work is not hours worked |
| Required to report to the shop to load the truck, then drive to Job A | At the shop | A required meeting place for instructions or tools starts the day, and travel from it is part of the day |
| Sent from Job A to Job B mid-shift | Already running | Travel from job site to job site during the workday counts |
| Finishes at Job B and drives home | Ended at Job B | Home travel after the last job is commute |
| Finishes at Job B and is required back at the shop | Ends at the shop | The return to the employer's premises is part of the day |
What should a foreman or office check each week?
Check that every shift's location lines add up to the shift length, that crew moves match what you scheduled, and that drives and supply runs are not sitting under a job by accident. A short list does it.
- Do each worker's location lines add up to their paid shift, with no minutes left over?
- Is every drive between sites on its own line, and is it paid?
- Do crew counts by jobsite match the schedule? Any worker moved mid-week should show on the day it happened.
- Are supply-house runs charged to the job the material was for, per your written rule?
- Do any days show one job for the whole shift when the worker is known to have moved?
- Are edits to allocations logged with a reason?
The foreman's version of this list is in the weekly timesheet checklist, and the daily headcount view is the daily manpower report. If you want a written policy for drives, start with a company drive time policy.
How ZeroBadge handles this
ZeroBadge places time by location. The badge reports about every 5 minutes, and each stretch is classified on site, in transit or other and allocated to a jobsite, with supplier stops drawn as locations. A move between sites stays one shift. Reports stored during a signal gap upload on reconnect with their original timestamps. ZeroBadge shows the minutes and you apply the pay and cost rules. More in multi-jobsite time tracking.
Frequently asked questions
How do I track employee hours when they work at more than one job site in a day?
Do I pay employees for driving between job sites?
Which job should a supply house run be charged to?
Should shop time be charged to a job?
How do I handle a worker who loses signal between sites?
Sources
- 1.29 CFR 785.38, Travel that is all in the day's work · Legal Information Institute, Cornell Law School (eCFR text)
- 2.29 CFR 785.35, Normal travel from home to work · Legal Information Institute, Cornell Law School (eCFR text)
- 3.Fact Sheet #22: Hours Worked Under the FLSA · U.S. Department of Labor, Wage and Hour Division
Keep reading
- SolutionMulti-jobsite time trackingSite transfers, transit and supply runs inside one shift record.
- GuideConstruction time tracking guideWhat to record, how the methods differ and what good time data looks like.
- GuideTravel time between job sites: pay rulesWhen drive time is paid and where state rules differ.
- GuideA drive time policy for contractorsWriting the rule down so every foreman applies it the same way.
- SolutionLabor cost trackingLoaded rates, job budgets and forecasts from badge-recorded hours.
- GuideConstruction job costing for laborTaking tracked hours to a job cost report.