Labor cost tracking for field crews

Know which projects are consuming your labor.

Tracking labor cost by job takes three things: the hours each worker spent at each jobsite, a loaded rate for each worker, and a budget to measure against. ZeroBadge supplies the hours automatically from badge-recorded shifts, applies the rates you set, and shows each job's labor cost, budget used, overtime cost and projected final hours at the current pace, with the jobs drifting over budget at the top of the list.

  • Labor cost by job, every week
  • Budget used against work complete
  • Jobs Needing Attention, askable in ZeroBadge AI

Jobs

Job labor · week

$72,608

Overtime cost

$5,736

Need attention

2 of 3

  • Riverside Medical Pavilion

    At risk

    Budget used 62% · work done 58%5,578 / 5,200 h (+7.3%)

    This week 375.0 h · $28,070 · OT $3,683

  • Northgate Tower

    Watch

    Budget used 44% · work done 44%9,702 / 9,600 h (+1.1%)

    This week 328.9 h · $24,008 · OT $1,672

  • Harbor Yard Distribution Center

    On track

    Budget used 71% · work done 73%7,234 / 7,400 h (−2.2%)

    This week 300.8 h · $20,530 · OT $380

Work complete, as entered · bar = budget hours used

Projected final = hours to date ÷ completion % entered by the project manager. Cost applies each worker's loaded hourly rate.

How labor job costing works

The inputs that decide whether a labor number can be trusted.

The method is standard. What usually breaks it is the first input: hours by job, written down after the fact.

  • Hours by job

    Recorded from badge-on to badge-off and allocated to the jobsite where each minute was spent. Shop, supplier and transit time stay on their own lines.

  • Loaded labor rate

    Set per worker by office admins: wage plus taxes, insurance and benefits. A worker with no rate shows as unknown cost, never as zero. To work the rate out, see how to calculate labor burden or try the labor burden calculator.

  • Overtime cost

    Your daily and weekly thresholds split each worker's hours into regular and overtime, and the premium is allocated across the jobs that worker's hours went to. See overtime tracking.

  • Budget and completion

    Enter a job's labor budget in hours, dollars or both, and update its percent complete. Projected final hours follow from the two.

  • Paid vs on-site time

    Every paid hour, side by side with the hours actually spent on a jobsite, so travel and stops are visible as a cost.

  • Who sees it

    Labor rates and cost are visible to office admins only. Supervisors and workers never see pay data.

Paid vs on-site time

Every paid hour, and where it was actually spent.

Labor cost by location for the week, at each worker's loaded rate: jobsites first, then the shop, supplier stops and transit between sites. The bar across the top shows how much of the paid week was spent on a jobsite.

Overtime is broken out by location too, so a premium that's building at one job shows up as that job's cost, not as a company-wide average that hides it.

Paid vs on site

Paid time · 1,045.2 h

On a jobsite 96.1%

  • Jobsite
  • Shop / office
  • Supplier stop
  • Between locations
  • RiversideJobsite375.0 hOT 38.3 h · $28,070
  • Harbor YardJobsite300.8 hOT 3.8 h · $20,530
  • NorthgateJobsite328.9 hOT 17.6 h · $24,008
  • ShopShop / office15.3 hOT 14.8 h · $1,496
  • Cascade SupplySupplier stop6.2 hOT 5.8 h · $386
  • Transit between locationsBetween locations19.0 hOT 15.4 h · $1,595

Loaded labor cost

$76,085

Overtime share

11.6%

OT hours at loaded rate + premium

Overtime rule shown: after 8 hours in a day or 40 regular hours in a week. Overtime cost adds a 0.5× premium on base wage to the loaded hourly rate. Your own payroll rules apply.

Projected final hours

How the projection is calculated, line by line.

Hours to date divided by the completion percentage your project manager entered. No modeled curve and no guessed progress: if completion isn't entered, ZeroBadge shows budget used and stops there.

Riverside Medical Pavilion · project to date

  1. Recorded before this week

    Badge-recorded hours to date

    2,860 h

  2. + This week

    Week of Oct 5, 2026

    375 h

  3. = Hours to date

    62% of the 5,200 h budget

    3,235 h

  4. ÷ Work complete

    Entered by the project manager, Fri Oct 9

    58%

  5. = Projected final hours

    At the current pace

    5,578 h

  6. − Labor budget

    Over by 7.3%

    +378 h

Labor at stake at this week's average loaded rate

378 h × $74.86 ≈ $28,297

A projection, not a prediction: it moves every time the completion figure is updated.

A job budget, week by week

Setting up a job budget takes four steps and one number you keep fresh.

The job-cost method is the same whether the job is a tenant improvement or a plant shutdown. The steps below are what you actually do in ZeroBadge, in the order that makes the later numbers trustworthy.

  1. 01

    Set the labor budget

    Enter the budget in hours, in dollars or in both. Take it from the bid: the hours you priced, and what you priced them at.

    Office admin · once per job

  2. 02

    Set loaded rates

    A rate for each worker who will charge the job. Leave a rate blank and that worker shows as unknown cost, so the total is flagged as incomplete instead of understated.

    Office admin · once per worker

  3. 03

    Let the badges record hours

    Hours at the jobsite arrive from the shifts. Nobody enters them by job code at the end of the week.

    Automatic · daily

  4. 04

    Enter percent complete

    The project manager updates it weekly. It is the one input that is an estimate, and the projection below is only as good as it is.

    Project manager · weekly

Worked arithmetic, with the assumptions labelled

Elm Street, week 5: budget used is 51.7%, work complete is 40%, projected labor is 29% over.

Assumptions, all invented for this example: a labor budget of 600 hours at an average loaded rate of $65 an hour, 310 hours recorded at the jobsite to date, and 40% complete as entered by the project manager. Overtime premium is left out to keep the sums readable.

  • Labor budget in dollars

    The sum

    600 h × $65

    The result

    $39,000

  • Labor cost to date

    The sum

    310 h × $65

    The result

    $20,150

  • Budget used

    The sum

    310 ÷ 600

    The result

    51.7%

  • Projected final hours

    The sum

    310 ÷ 0.40

    The result

    775 hours

  • Projected variance in hours

    The sum

    775 - 600

    The result

    +175 h, which is 29.2% over budget

  • Projected final labor cost

    The sum

    775 h × $65

    The result

    $50,375, or $11,375 over the $39,000 budget

Budget used is ahead of work complete by 11.7 points, and that gap is the early warning. The projection assumes the rest of the job burns hours at the pace the first 40% did, so a job with a slow start and a fast finish will read worse than it ends up. Re-enter the completion each week and watch whether the projected final hours settle or keep climbing.

Decisions for ops and finance

What ops and finance do with each number.

  • Budget used is ahead of work complete

    What ZeroBadge shows

    Hours used against the labor budget, next to the completion you entered.

    The decision

    Re-sequence or re-staff the job while most of the work is still ahead.

  • Projected final hours exceed the budget

    What ZeroBadge shows

    The projection, the variance in hours and percent, and the job's status in Jobs Needing Attention.

    The decision

    Price a change order for added scope, or reset the forecast with the owner before closeout.

  • Overtime cost concentrated on one job

    What ZeroBadge shows

    Overtime hours and premium cost by job and by week.

    The decision

    Add a crew member or move one over, instead of paying the premium for the rest of the phase.

  • A gap between paid and on-site time

    What ZeroBadge shows

    Transit, shop and supplier time as hours and labor cost.

    The decision

    Stage material on site, batch supply runs, or change which crew covers which job.

  • Labor variance month to month

    What ZeroBadge shows

    Weekly labor cost and hours by job, with change against the prior period.

    The decision

    Support WIP reporting and over/under billing with recorded hours instead of estimates.

  • Final labor by job at closeout

    What ZeroBadge shows

    Recorded hours and loaded cost for the finished job, week by week.

    The decision

    Feed real labor back into the next bid for similar work.

Scope

ZeroBadge supplies the labor side of job cost. Your accounting system keeps the books.

Materials, equipment, subcontracts and the general ledger stay where they are. ZeroBadge gives your job cost reports badge-recorded hours by job, cost at your loaded rates and a forecast you can explain, and the same hours go to payroll through the payroll integration.

ZeroBadge AI

Ask ZeroBadge AI which jobs are running hot

Ask about budget the way you would ask your estimator. ZeroBadge AI works from labor hours and cost rates already in your records, shows the arithmetic and cannot alter a budget or a timesheet. Admins decide who can use it.

  • You ask

    Which jobs need attention on labor budget?

    One. The Harbor Road clinic has used 74% of its labor budget with 58% of the work marked complete. Elm Street is at 52% used against 55% complete, so it is on pace.

  • You ask

    What is the labor cost for Pine Ridge this month?

    $38,400 across 640 hours, an average of $60 an hour. Workers with no cost rate set show as unknown cost, never as zero.

  • You ask

    How much paid time last week was not on a jobsite?

    98 of 1,310 paid hours, about 7.5%, were transit or other. 64 hours were drive time between sites and 34 hours were supplier or other stops.

Answers come only from your company's own records. Every number links to the records behind it. Read-only; admins control access.

How ZeroBadge AI works

Questions

Questions about labor cost tracking.

How do you track labor costs on a construction or field project?
Record hours by job as they happen, multiply them by a loaded rate for each worker, add the overtime premium where overtime was worked, and compare the total against the job's labor budget during the job, not after it.
What is a burdened labor rate, and why use it for job costing?
It's the wage plus what the hour actually costs you: payroll taxes, workers' comp, insurance and benefits. Costing a job at base wage understates labor, so budgets and bids built on it look better than reality.
How is projected final labor calculated?
Hours recorded to date divided by the percent complete your project manager entered. Compare the result with the labor budget to get the projected variance. It updates whenever new hours are recorded or completion changes.
How do job-cost hours relate to the hours sent to payroll?
The same recorded hours feed both. A manager approves the week in the timesheet approval workflow, approved hours go to your payroll provider, and the hours by jobsite behind them are what the job-cost numbers use.
Is drive time between jobsites charged to a job?
ZeroBadge records it as transit, separately from site time, so you decide how to code it. See tracking drive time between job sites for the policy side and multi-jobsite time tracking for how transit is measured.

Last updated

Get started

See your jobs against their labor budgets.

We'll set up a walkthrough with your jobs, rates and budgets: labor cost by job, forecasts and the jobs that need attention.

What we will walk through

  • 01Loaded rates and labor cost by job
  • 02Budget used, completion and projected final hours
  • 03Overtime cost and paid vs on-site time