What is a manpower report in construction?
A manpower report is a daily record of how many workers each company had on a project, by trade or craft, and the hours they worked, usually with the work they were doing. General contractors and owners ask subcontractors for it to compare staffing with the schedule. It lists counts and hours, not wages, which separates it from certified payroll.
Last updated By ZeroBadge
What is a manpower report?
A manpower report is a short daily record of who was on the job: how many people, in which trade or craft, for how many hours, doing what. It is often one section of a larger daily report. It answers a staffing question the schedule cannot: were enough people here today to do the work planned for today?
Owners publish their own forms. One example is a university owner's contractor quality control daily report, which lists for each activity the contractor or subcontractor, the equipment, the trade or craft, the number of workers and the total hours worked, and then totals the day's hours across every craft (University of Washington, CPD Form 01 45 00). It has no column for a worker's name or wage rate.
Your contract or the project specifications say whether you owe one and in what format. The words differ from job to job: manpower report, labor report, daily log, crew count. Read the general conditions before you assume it is optional.
Who asks for a manpower report and what do they do with it?
The general contractor or construction manager asks most often, and the owner and sometimes a lender read it. Each uses it to answer a different question, and knowing which one is asking tells you how much detail the report needs.
| Reader | Question it answers | What they look for |
|---|---|---|
| General contractor or superintendent | Is each sub staffed for today's work, and is the look-ahead realistic? | Counts by trade against the schedule, and a sub that is short |
| Owner or owner's representative | Is the contractor putting the labor on the job it said it would? | Total hours, trends week over week |
| Your own project manager | Is the labor on this job tracking the estimate? | Hours by code and by day, behind the report |
| Anyone reconstructing a delay later | What was the staffing on a given date? | A dated, signed record that was written at the time |
What fields does a manpower report carry?
At minimum it carries the date, the project and area, the company, the trade or craft, the number of workers and the hours worked. Forms add the activity, equipment and a signature. Most of these are already in your timesheet record, which is what makes the report a copy job and not a second data entry.
| Field | Why it is asked | Where it comes from in your records |
|---|---|---|
| Date and project | To tie the report to the schedule | The day's timesheets, filtered to the jobsite |
| Company and tier | To separate subs and their sub-tiers | Your own roster |
| Trade or craft | To compare against the look-ahead by trade | Worker classification: foreman, journeyman, apprentice |
| Number of workers | Headcount on this site today | Attendance by jobsite for the day |
| Hours worked | To total labor and compare to the estimate | On-site hours by jobsite from the timesheet |
| Work in progress | To tie the labor to an activity | The foreman's note or the cost code |
| Equipment | Some forms ask for it | Dispatch or the foreman |
| Notes and delays | To record weather, waiting and access issues | The foreman, written the same day |
| Signature | To make the report a record someone stands behind | The foreman or superintendent |
Do you report headcount or hours?
Report both, counted per jobsite, and write down how you count a worker who moved. A headcount says how many people were present, hours say how much work they gave this site, and neither alone describes the day. The trap is the worker who splits a day between two sites: he is present at both, so site lines add up to more people than you employ.
| Trade or craft | People at Site A | Hours at Site A |
|---|---|---|
| Foreman | 1 | 8.5 |
| Journeyman (4 all day, 1 who left for Site B after 5.0 h) | 5 | 39.0 |
| Apprentice | 2 | 17.0 |
| Site A total | 8 | 64.5 |
Reconciling two site reports to the paid shift (illustrative)
- Site A, from the table above
- 8 people, 64.5 h
- Site B: one journeyman all day (8.5 h), the one who moved (3.0 h), one apprentice (8.5 h)
- 3 people, 20.0 h
- Site lines added together
- 11 people, 84.5 h
- Drive between sites, belonging to neither site
- 0.5 h
- Roster for the day: 1 foreman, 6 journeymen, 3 apprentices
- 10 people
- Paid shift: 10 workers × 8.5 h
- 85.0 h
- Hours: 84.5 + 0.5 = 85.0. People: 11 lines, 10 workers
- One person counted at both sites
The 11 is correct for each site's report and the 10 is correct for your payroll. Put a footnote on the report so nobody reads the difference as an error.
Some forms ask for full-time equivalents instead, which is hours divided by the length of a full day. Site A's 64.5 hours is 7.6 equivalents at 8.5 hours and 8.1 at 8.0. Ask which day length the GC means before you divide.
How is a daily manpower report different from weekly and certified payroll reports?
The daily report is a staffing count, the weekly summary rolls the same counts up to hours, and certified payroll is a wage record that names each worker. They answer different questions and are produced for different readers, so one does not replace another.
| Daily manpower report | Weekly manpower summary | Certified payroll | |
|---|---|---|---|
| Cadence | Every working day | Once a week | Every week on covered work |
| Lists | Headcount and hours by trade | Hours by trade and day, headcount trend | Each worker by name, classification, daily and weekly hours, rates and deductions |
| Names workers? | No | No | Yes, with a partial identifier |
| Wages? | No | No | Yes |
| Required by | Your contract or the owner's spec | Your contract or the GC | Federal or federally assisted construction contracts under the Davis-Bacon and Related Acts |
| Signed | Usually by the foreman or superintendent | Usually the project manager | A Statement of Compliance accompanies each one |
How does a subcontractor produce a manpower report without double entry?
Take the counts and hours from the same record that feeds payroll, check them against the foreman's own count, and send the report at the same time each day. A manpower report that is typed from a separate notebook is the version that disagrees with the timesheet at the end of the week.
- 1
Decide the cutoff
A report due at 3:00 PM needs a record that is current at 3:00 PM. A record that only completes after the shift cannot feed it.
- 2
Pull counts and hours by jobsite
Per trade, per site. Use on-site hours, and show drive time separately so it does not inflate either site.
- 3
Have the foreman compare it with his own count
Differences of one head are normal. A difference of three means a worker is on the wrong site in the record or the foreman has someone not in it.
- 4
Sign and send it
Same format, same time. A report that arrives at a different hour every day gets read at a different quality.
- 5
Keep a copy with the week's records
You will want it when the week is approved and, occasionally, a year later.
What makes a manpower report wrong?
| Error | What it does | Fix |
|---|---|---|
| Counting the scheduled crew, not the present crew | Overstates labor on days people are out | Count from attendance, not the schedule |
| Counting a worker once when he split a day | Understates each site's staffing | Count him at each site he worked, with the hours he gave it |
| Folding drive time into a site | Inflates one site's hours | Show transit separately or by your stated rule |
| Mixing in sub-tier labor | Double counts people the GC also counts | Report your own crew and your sub-tiers on separate lines |
| Rounding every worker to eight hours | Hides short days and overtime | Report the recorded hours |
| Writing it from memory the next morning | Weakens it as a record | Send it the same day from the record |
How ZeroBadge handles this
ZeroBadge supplies the counts and hours: every minute of a shift is classified on site, in transit or other and allocated to a jobsite, so attendance and on-site hours by jobsite come from the shift record and not from a separate notebook. A worker who moves is counted at each site with the hours given to it, and transit shows on its own line. ZeroBadge does not fill in a GC's form. You copy the counts onto the form the project requires. See jobsite attendance tracking.
Frequently asked questions
What is the difference between a manpower report and certified payroll?
Is a manpower report the same as a daily report?
Do I count a worker who was on site for one hour?
Who has to submit a manpower report?
How should a worker who splits a day between two sites be reported?
Sources
- 1.Contractor Quality Control Daily Report, CPD Form 01 45 00 (rev. 07/05/17) · University of Washington, Capital Planning and Development
- 2.Form WH-347, Payroll (For Contractor's Optional Use) · U.S. Department of Labor, Wage and Hour Division
Keep reading
- SolutionJobsite attendance trackingScheduled against present, and the reason for every gap.
- SolutionDaily manpower reportsCounts and hours by jobsite from the shift record.
- GlossaryManpower report, definedA short definition and the terms it connects to.
- GuideCertified payroll explainedThe weekly wage record on public works jobs.
- GuideForeman weekly timesheet checklistThe end-of-week steps that keep the daily numbers and the week in agreement.
- SolutionConstruction crew trackingA live view of who is on which site, set against the weekly record.