What is a manpower report in construction?

A manpower report is a daily record of how many workers each company had on a project, by trade or craft, and the hours they worked, usually with the work they were doing. General contractors and owners ask subcontractors for it to compare staffing with the schedule. It lists counts and hours, not wages, which separates it from certified payroll.

Last updated By ZeroBadge

What is a manpower report?

A manpower report is a short daily record of who was on the job: how many people, in which trade or craft, for how many hours, doing what. It is often one section of a larger daily report. It answers a staffing question the schedule cannot: were enough people here today to do the work planned for today?

Owners publish their own forms. One example is a university owner's contractor quality control daily report, which lists for each activity the contractor or subcontractor, the equipment, the trade or craft, the number of workers and the total hours worked, and then totals the day's hours across every craft (University of Washington, CPD Form 01 45 00). It has no column for a worker's name or wage rate.

Your contract or the project specifications say whether you owe one and in what format. The words differ from job to job: manpower report, labor report, daily log, crew count. Read the general conditions before you assume it is optional.

Who asks for a manpower report and what do they do with it?

The general contractor or construction manager asks most often, and the owner and sometimes a lender read it. Each uses it to answer a different question, and knowing which one is asking tells you how much detail the report needs.

Who reads the daily manpower report and why
ReaderQuestion it answersWhat they look for
General contractor or superintendentIs each sub staffed for today's work, and is the look-ahead realistic?Counts by trade against the schedule, and a sub that is short
Owner or owner's representativeIs the contractor putting the labor on the job it said it would?Total hours, trends week over week
Your own project managerIs the labor on this job tracking the estimate?Hours by code and by day, behind the report
Anyone reconstructing a delay laterWhat was the staffing on a given date?A dated, signed record that was written at the time
The last row is why a report written on the day carries more weight than one rebuilt weeks later from memory.

What fields does a manpower report carry?

At minimum it carries the date, the project and area, the company, the trade or craft, the number of workers and the hours worked. Forms add the activity, equipment and a signature. Most of these are already in your timesheet record, which is what makes the report a copy job and not a second data entry.

Typical fields and where a subcontractor gets each one
FieldWhy it is askedWhere it comes from in your records
Date and projectTo tie the report to the scheduleThe day's timesheets, filtered to the jobsite
Company and tierTo separate subs and their sub-tiersYour own roster
Trade or craftTo compare against the look-ahead by tradeWorker classification: foreman, journeyman, apprentice
Number of workersHeadcount on this site todayAttendance by jobsite for the day
Hours workedTo total labor and compare to the estimateOn-site hours by jobsite from the timesheet
Work in progressTo tie the labor to an activityThe foreman's note or the cost code
EquipmentSome forms ask for itDispatch or the foreman
Notes and delaysTo record weather, waiting and access issuesThe foreman, written the same day
SignatureTo make the report a record someone stands behindThe foreman or superintendent

Do you report headcount or hours?

Report both, counted per jobsite, and write down how you count a worker who moved. A headcount says how many people were present, hours say how much work they gave this site, and neither alone describes the day. The trap is the worker who splits a day between two sites: he is present at both, so site lines add up to more people than you employ.

A mechanical subcontractor's Tuesday on two sites, Site A by trade (illustrative)
Trade or craftPeople at Site AHours at Site A
Foreman18.5
Journeyman (4 all day, 1 who left for Site B after 5.0 h)539.0
Apprentice217.0
Site A total864.5

Reconciling two site reports to the paid shift (illustrative)

Site A, from the table above
8 people, 64.5 h
Site B: one journeyman all day (8.5 h), the one who moved (3.0 h), one apprentice (8.5 h)
3 people, 20.0 h
Site lines added together
11 people, 84.5 h
Drive between sites, belonging to neither site
0.5 h
Roster for the day: 1 foreman, 6 journeymen, 3 apprentices
10 people
Paid shift: 10 workers × 8.5 h
85.0 h
Hours: 84.5 + 0.5 = 85.0. People: 11 lines, 10 workers
One person counted at both sites

The 11 is correct for each site's report and the 10 is correct for your payroll. Put a footnote on the report so nobody reads the difference as an error.

Some forms ask for full-time equivalents instead, which is hours divided by the length of a full day. Site A's 64.5 hours is 7.6 equivalents at 8.5 hours and 8.1 at 8.0. Ask which day length the GC means before you divide.

How is a daily manpower report different from weekly and certified payroll reports?

The daily report is a staffing count, the weekly summary rolls the same counts up to hours, and certified payroll is a wage record that names each worker. They answer different questions and are produced for different readers, so one does not replace another.

Three reports that sound alike
Daily manpower reportWeekly manpower summaryCertified payroll
CadenceEvery working dayOnce a weekEvery week on covered work
ListsHeadcount and hours by tradeHours by trade and day, headcount trendEach worker by name, classification, daily and weekly hours, rates and deductions
Names workers?NoNoYes, with a partial identifier
Wages?NoNoYes
Required byYour contract or the owner's specYour contract or the GCFederal or federally assisted construction contracts under the Davis-Bacon and Related Acts
SignedUsually by the foreman or superintendentUsually the project managerA Statement of Compliance accompanies each one
The DOL describes certified payroll, and WH-347 as an optional form for it, on its WH-347 page. For public works see certified payroll explained.

How does a subcontractor produce a manpower report without double entry?

Take the counts and hours from the same record that feeds payroll, check them against the foreman's own count, and send the report at the same time each day. A manpower report that is typed from a separate notebook is the version that disagrees with the timesheet at the end of the week.

  1. 1

    Decide the cutoff

    A report due at 3:00 PM needs a record that is current at 3:00 PM. A record that only completes after the shift cannot feed it.

  2. 2

    Pull counts and hours by jobsite

    Per trade, per site. Use on-site hours, and show drive time separately so it does not inflate either site.

  3. 3

    Have the foreman compare it with his own count

    Differences of one head are normal. A difference of three means a worker is on the wrong site in the record or the foreman has someone not in it.

  4. 4

    Sign and send it

    Same format, same time. A report that arrives at a different hour every day gets read at a different quality.

  5. 5

    Keep a copy with the week's records

    You will want it when the week is approved and, occasionally, a year later.

What makes a manpower report wrong?

Common errors and the fix
ErrorWhat it doesFix
Counting the scheduled crew, not the present crewOverstates labor on days people are outCount from attendance, not the schedule
Counting a worker once when he split a dayUnderstates each site's staffingCount him at each site he worked, with the hours he gave it
Folding drive time into a siteInflates one site's hoursShow transit separately or by your stated rule
Mixing in sub-tier laborDouble counts people the GC also countsReport your own crew and your sub-tiers on separate lines
Rounding every worker to eight hoursHides short days and overtimeReport the recorded hours
Writing it from memory the next morningWeakens it as a recordSend it the same day from the record

How ZeroBadge handles this

ZeroBadge supplies the counts and hours: every minute of a shift is classified on site, in transit or other and allocated to a jobsite, so attendance and on-site hours by jobsite come from the shift record and not from a separate notebook. A worker who moves is counted at each site with the hours given to it, and transit shows on its own line. ZeroBadge does not fill in a GC's form. You copy the counts onto the form the project requires. See jobsite attendance tracking.

Frequently asked questions

What is the difference between a manpower report and certified payroll?
A manpower report counts workers and hours by trade, daily, for staffing. Certified payroll is a weekly wage record for covered public works that names each worker, with classification, hours, rates and deductions, and a signed Statement of Compliance (DOL WH-347 page).
Is a manpower report the same as a daily report?
Not exactly. The manpower report is usually one section of a daily report, which also covers work in progress, inspections, tests and weather. Some owners' forms combine them, as in the University of Washington example, and some GCs ask for the labor count alone.
Do I count a worker who was on site for one hour?
Count anyone who was present on that site, with the hours they gave it, unless your contract says otherwise. Hours make a short visit visible, so the count does not overstate the labor.
Who has to submit a manpower report?
Your contract or the project specifications decide. General contractors commonly require it from subcontractors, and owners can require it from the prime. Read the general conditions and the daily reporting section of the spec.
How should a worker who splits a day between two sites be reported?
At both sites, with the hours worked at each. The site reports will add up to one more person than you employ, which is correct. Add a footnote so the difference is not read as an error.

Sources

  1. 1.Contractor Quality Control Daily Report, CPD Form 01 45 00 (rev. 07/05/17) · University of Washington, Capital Planning and Development
  2. 2.Form WH-347, Payroll (For Contractor's Optional Use) · U.S. Department of Labor, Wage and Hour Division

Get started

See ZeroBadge on your workforce.

Tell us how your crews work today. We will show you a badge-recorded week built from your own jobsites.

What we will walk through

  • 01How the badge records a shift
  • 02Your jobsites as geofences
  • 03The weekly timesheet and approval
  • 04Sending approved hours to payroll