Glossary · Job costing

Job costing

Job costing is the practice of recording what each job actually costs, in labor, materials, equipment and subcontractors, and comparing it with the estimate. The comparison shows where a job is making or losing money while there is still time to act on it.

Last updated

How does job costing work?

Job costing works by giving every job a budget broken into lines, then posting real costs to those lines as they happen. Labor is usually the largest and the least certain line, because it depends on hours that someone has to record.

  1. 1

    Budget by line

    The estimate is split into cost codes, each with hours and dollars.

  2. 2

    Post actuals

    Approved hours times a loaded labor rate, plus material, equipment and subcontractor invoices, are posted to the same lines.

  3. 3

    Compare and act

    The office checks actual against budget weekly, not at job close, and changes staffing or pricing on the next phase.

What does job costing show on a real job?

Labor on a 6-week tenant improvement

Estimated labor
480 hours at a $52 loaded rate = $24,960
Actual after 4 weeks
410 hours at $52 = $21,320
Share of the 6-week estimate used
410 ÷ 480 = 85% of hours, with 33% of the schedule left
Projected overrun if the pace holds
(410 ÷ 4) × 6 = 615 hours, which is 135 over estimate

Illustrative numbers. Whether the pace holds depends on the work remaining, so treat a projection as a prompt to look, not a verdict.

The result is only as good as the hours behind it. Where the hours come from a handwritten sheet filled in on Friday, the job cost report inherits the guessing.

Frequently asked questions

What is the difference between job costing and estimating?
Estimating predicts what a job will cost. Job costing records what it actually costs. The two are compared so that the next estimate improves.
How often should job costs be reviewed?
Weekly is common on active jobs. Reviewing only at job close shows the loss after it has already happened.
Why is labor the hardest line to cost?
Material arrives with an invoice. Labor depends on hours that someone has to record correctly and assign to the right job and code.

Get started

See ZeroBadge on your workforce.

Tell us how your crews work today. We will show you a badge-recorded week built from your own jobsites.

What we will walk through

  • 01How the badge records a shift
  • 02Your jobsites as geofences
  • 03The weekly timesheet and approval
  • 04Sending approved hours to payroll