Loaded labor rate

A loaded labor rate is the full hourly cost of a worker to the company: the wage plus labor burden such as payroll taxes, insurance and benefits. Bids and job cost reports use it instead of the wage because the company pays the whole amount for every hour.

Last updated

How is a loaded labor rate calculated?

A loaded labor rate is calculated by adding burden to the hourly wage. The simple version multiplies the wage by one plus the burden percentage. The careful version divides total yearly cost by the hours the company actually gets.

A pipefitter paid $45 an hour

Wage
$45.00
Burden at 30%
$45.00 × 0.30 = $13.50
Loaded rate per paid hour
$45.00 + $13.50 = $58.50

Illustrative numbers. Substitute your own burden percentage.

Frequently asked questions

Is a loaded labor rate the same as a billing rate?
No. The loaded rate is the company's cost per hour. The billing rate is what the customer pays and includes overhead and profit on top of that cost.
Should a loaded labor rate use paid hours or productive hours?
Either works if you use the same basis everywhere. Productive hours give a higher rate and tend to match what a job really costs; paid hours are easier to calculate.
Where do the hours come from?
From timesheets. A loaded rate multiplied by approved hours for each worker and jobsite gives labor cost for the job.

Get started

See ZeroBadge on your workforce.

Tell us how your crews work today. We will show you a badge-recorded week built from your own jobsites.

What we will walk through

  • 01How the badge records a shift
  • 02Your jobsites as geofences
  • 03The weekly timesheet and approval
  • 04Sending approved hours to payroll